Six months ago, Piedmont voters defeated the $13.5 bond measure (Measure H) to rejuvenate the school district’s Alan Harvey Theater, a major disappointment to its ardent supporters. In hindsight, the results might have been different if the school district had been more forthright in its communications and thorough in its planning. There was no lack of public outreach. But information and advice provided to the Board and public by the district’s staff, committees, and consultants all too often was incomplete or misleading, resulting in flawed decisions. Among other items, the Board was persuaded to authorize $360,000 for the preparation of design development drawings without waiting for the outcome of the election, a high-risk decision with marginal benefit.
What began in 2005 as a $5.4 million renovation was changed in 2012 into a $9.8 million theater remodel plus a whole new wing, based on a plan volunteered by designer Mark Becker. A 17-member committee supported the expanded program and declared that “Piedmont High School should be thought of as a performing arts high school”, meaning that performing arts would become the academic focus.
The new wing included a corridor with wheel-chair access to the auditorium, an elaborate instructional classroom, and improved backstage facilities. The balance of the project consisted of remodeling the existing theater. In all of the district communications, there is not a single meeting note, resolution, letter, or ballot measure statement that informed anyone that seating capacity would be reduced from 500 to 320 seats, a loss of 180 seats. This meant three school assemblies instead of two would be required for student body presentations and a smaller audience capacity for theatrical productions.
About 50 good seats were necessarily lost in providing a cross-aisle for wheel-chair access, but over 100 were lost in changing from “continental” (no center aisles) to conventional seating and in moving the control room into the auditorium instead of in a loft above the lobby. Forty-five temporary seats would have been above the orchestra pit with very poor sight lines. A smaller audience capacity would have resulted in loss in rental revenue, which partially offsets the cost of theater management and other operating expenses.
Curiously, the program committee did not mention improvement in acoustics (nor did the ballot measure), but the theater consultant in an appendix suggested adjustable acoustic draperies for the glass windows. The consultant did not, however, recommend the installation of plastic “clouds” in the ceiling as shown in the architect’s illustrations. No concern was expressed for the destruction of architectural symmetry in the auditorium or in the 50% loss in the windows that provide daylight when the curtains are open.
The district implied that the theater could not continue in use if the bond measure failed. Although it is not wheel chair accessible, the theater can legally continue in use as long as the community is willing to tolerate its various deficiencies, many of which are matters of deferred maintenance, such as the leaking roof. If the theater were unsafe, it would have been shut down.
Many voters were concerned about the cost of the project. District staff, aided by consultants, added essential items such as fees and contingencies to the original estimate of $9.8 million ($560 per square foot) and arrived at a total budget of $14.5 million. When the cost of debt service is added, the total project cost came to over $20 million —about $1,200 per square foot. Cost comparisons made with three other school theater “renovation” projects were virtually meaningless because the other theaters had twice the seating capacity and very different scopes of work.
Vila Construction’s construction cost estimate, incidentally, was 15% lower than the architect’s estimate. Had the Vila estimate been used, the bond measure would have been $11.5 million rather than $13.5 million. The “hybrid” bond option chosen by the Board deferred payment on the principal for six years in order to reduce the immediate impact on taxpayers, but added over one million dollars to the debt service.
It would have behooved the district at the outset to establish a project schedule that started construction promptly at the end of a school year, rather than in the middle. This would have allowed two full summer months for site preparation and demolition in good weather with minimum disruption to campus activity. Rental of interim theater and classroom facilities would then have been during one school year rather than portions of two years.
There is no pleasure in calling attention to these missteps. However, the needless loss in time, money and human energy over a two-year period cannot be ignored. The next election in November 2016 gives the district ample time to review its internal procedures and take corrective steps. The district has everything to be gained by thorough planning and full disclosure of issues to a generous, involved, and supportive parent community.
William Blackwell – Piedmont Resident and Retired Architect
Editors’ Note: The opinions expressed are those of the author and not necessarily those of the Piedmont Civic Association.